Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study
Main Author: | |
---|---|
Publication Date: | 2014 |
Other Authors: | |
Format: | Article |
Language: | eng |
Source: | Repositórios Científicos de Acesso Aberto de Portugal (RCAAP) |
Download full: | http://hdl.handle.net/1822/31076 |
Summary: | Cost overrun in construction projects is a common issue affecting project performance, and Gas-Oil construction projects in Iran are no exception. This paper presents the results of a questionnaire conducted to identify and evaluate the relative importance of the significant factors contributing to the Gas-Oil construction industry of Iran as a case study for developing countries. The survey respondents included project owners, contractors and consultants involved in Iranian Gas-Oil construction projects. The results of the survey revealed that the main causes of cost overrun in this industry include inaccurate cost estimations, improper planning, frequent design changes, inadequate labour/skill availability, inflation of costs of machinery, labour, raw material and transportation prices. The first three factors are the project consultants' responsibilityand the appointment of qualified consultants and personnel training are strongly recommended to alleviate cost overrun. The paper also reviews and compares findings of a set of similar researches in a number of developing countries. |
id |
RCAP_7e56cb53f32244c61486fd8d2c0b23e6 |
---|---|
oai_identifier_str |
oai:repositorium.sdum.uminho.pt:1822/31076 |
network_acronym_str |
RCAP |
network_name_str |
Repositórios Científicos de Acesso Aberto de Portugal (RCAAP) |
repository_id_str |
https://opendoar.ac.uk/repository/7160 |
spelling |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case studyCost issuesDeveloping countriesGas-OilIranCost overrun in construction projects is a common issue affecting project performance, and Gas-Oil construction projects in Iran are no exception. This paper presents the results of a questionnaire conducted to identify and evaluate the relative importance of the significant factors contributing to the Gas-Oil construction industry of Iran as a case study for developing countries. The survey respondents included project owners, contractors and consultants involved in Iranian Gas-Oil construction projects. The results of the survey revealed that the main causes of cost overrun in this industry include inaccurate cost estimations, improper planning, frequent design changes, inadequate labour/skill availability, inflation of costs of machinery, labour, raw material and transportation prices. The first three factors are the project consultants' responsibilityand the appointment of qualified consultants and personnel training are strongly recommended to alleviate cost overrun. The paper also reviews and compares findings of a set of similar researches in a number of developing countries. Taylor and FrancisUniversidade do MinhoDerakhshanalavijeh, RoyaTeixeira, José M. Cardoso2014-112014-11-01T00:00:00Zinfo:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/articleapplication/pdfhttp://hdl.handle.net/1822/31076eng1392-3730info:eu-repo/semantics/openAccessreponame:Repositórios Científicos de Acesso Aberto de Portugal (RCAAP)instname:FCCN, serviços digitais da FCT – Fundação para a Ciência e a Tecnologiainstacron:RCAAP2024-05-11T07:03:04Zoai:repositorium.sdum.uminho.pt:1822/31076Portal AgregadorONGhttps://www.rcaap.pt/oai/openaireinfo@rcaap.ptopendoar:https://opendoar.ac.uk/repository/71602025-05-28T16:13:46.195391Repositórios Científicos de Acesso Aberto de Portugal (RCAAP) - FCCN, serviços digitais da FCT – Fundação para a Ciência e a Tecnologiafalse |
dc.title.none.fl_str_mv |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study |
title |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study |
spellingShingle |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study Derakhshanalavijeh, Roya Cost issues Developing countries Gas-Oil Iran |
title_short |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study |
title_full |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study |
title_fullStr |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study |
title_full_unstemmed |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study |
title_sort |
Causes of cost overrun in construction projects in developing countries: Gas-oil construction industry of Iran, a case study |
author |
Derakhshanalavijeh, Roya |
author_facet |
Derakhshanalavijeh, Roya Teixeira, José M. Cardoso |
author_role |
author |
author2 |
Teixeira, José M. Cardoso |
author2_role |
author |
dc.contributor.none.fl_str_mv |
Universidade do Minho |
dc.contributor.author.fl_str_mv |
Derakhshanalavijeh, Roya Teixeira, José M. Cardoso |
dc.subject.por.fl_str_mv |
Cost issues Developing countries Gas-Oil Iran |
topic |
Cost issues Developing countries Gas-Oil Iran |
description |
Cost overrun in construction projects is a common issue affecting project performance, and Gas-Oil construction projects in Iran are no exception. This paper presents the results of a questionnaire conducted to identify and evaluate the relative importance of the significant factors contributing to the Gas-Oil construction industry of Iran as a case study for developing countries. The survey respondents included project owners, contractors and consultants involved in Iranian Gas-Oil construction projects. The results of the survey revealed that the main causes of cost overrun in this industry include inaccurate cost estimations, improper planning, frequent design changes, inadequate labour/skill availability, inflation of costs of machinery, labour, raw material and transportation prices. The first three factors are the project consultants' responsibilityand the appointment of qualified consultants and personnel training are strongly recommended to alleviate cost overrun. The paper also reviews and compares findings of a set of similar researches in a number of developing countries. |
publishDate |
2014 |
dc.date.none.fl_str_mv |
2014-11 2014-11-01T00:00:00Z |
dc.type.status.fl_str_mv |
info:eu-repo/semantics/publishedVersion |
dc.type.driver.fl_str_mv |
info:eu-repo/semantics/article |
format |
article |
status_str |
publishedVersion |
dc.identifier.uri.fl_str_mv |
http://hdl.handle.net/1822/31076 |
url |
http://hdl.handle.net/1822/31076 |
dc.language.iso.fl_str_mv |
eng |
language |
eng |
dc.relation.none.fl_str_mv |
1392-3730 |
dc.rights.driver.fl_str_mv |
info:eu-repo/semantics/openAccess |
eu_rights_str_mv |
openAccess |
dc.format.none.fl_str_mv |
application/pdf |
dc.publisher.none.fl_str_mv |
Taylor and Francis |
publisher.none.fl_str_mv |
Taylor and Francis |
dc.source.none.fl_str_mv |
reponame:Repositórios Científicos de Acesso Aberto de Portugal (RCAAP) instname:FCCN, serviços digitais da FCT – Fundação para a Ciência e a Tecnologia instacron:RCAAP |
instname_str |
FCCN, serviços digitais da FCT – Fundação para a Ciência e a Tecnologia |
instacron_str |
RCAAP |
institution |
RCAAP |
reponame_str |
Repositórios Científicos de Acesso Aberto de Portugal (RCAAP) |
collection |
Repositórios Científicos de Acesso Aberto de Portugal (RCAAP) |
repository.name.fl_str_mv |
Repositórios Científicos de Acesso Aberto de Portugal (RCAAP) - FCCN, serviços digitais da FCT – Fundação para a Ciência e a Tecnologia |
repository.mail.fl_str_mv |
info@rcaap.pt |
_version_ |
1833595818167238656 |